Dec/Jan/Feb 2024/5
Brickwork and Lighting
The major achievement in this period was the removal of the loose brickwork that had become detached from the buttresses of the two magazines at Clem due to frost action and penetration by vegetation roots. If this had been left, it would have further deteriorated and could have ultimately collapsed. The vegetation on and adjacent to the brickwork was sympathetically cleared to allow access and remove roots, etc. The detached brickwork was removed using small tools to minimise vibration damage to the rest of the structure. The surfaces were cleaned and prepared for our partner bricklayer, Brickguru, to rebuild the structures starting in early April. Once complete and cured, the brickwork will be thoroughly cleaned and treated to repel moisture and to prevent further vegetation growth, which should ensure its integrity for decades to come.
This period also saw the completion of the Wanstone power project, with the installation of lighting in the Jane compressor room and lamp room. The initial design work took place in 2019, but Covid-19 prevented progress through much of 2020 and 2021. The substation was connected in June 2022, and buildings were gradually energised, leaving the final two needing a short underground cable installation. This was completed in late January and the power connected by our electrician, making this the first time these buildings had seen an electricity supply for over 60 years.

